NEWS
Celebrating Our Milestones of Success
PRESENT (UNDER PROGRESS)
Reinforced Concrete (RC) works
Ballast supply and compaction
Office, B class warehouse and mechanization construction works
Outdoor drainage systems
Outdoor electrical works contract
Existing power cable relocation
Updating A Class MEP drawings preparation
Awarding and contracting MEP contractor
RC wall works
Water reservoir construction
Fencing
Trees replanting and cutting
April 2024 (COMPLETED)
Build Permit obtained
March 2024 (COMPLETED)
AD Ports Group acquires majority stake in Tbilisi Dry Port. For more information, please check it out here.
Q3 2023 (COMPLETED)
Urban Design Review Panel (UDRP)
Paving of the territory
Supply of territory ballast
Ground Excavation works
Purchase of Equipment
Mechanization building
Railway construction
Suppliers of dock levers, sectional door, outdoor lighting system have been selected
2022 - Q2 2023 (COMPLETED)
Railway link between the main station and the Dry Port premises
Gravelling and leveling works